UZBEKISTAN GAS TO LIQUID PROJECT (UZGTL)

METHODOLOGY FOR DESIGN AND EXECUTION

OF THE AS-BUILT DOCUMENTATION

(STORAGE TANKS)



UZGTL-EEN-MEC-PC-00-0-0001

00

E




Rev

Description

Date

Prepared

Checked

Approved

00

Issued for review

09.08.2018

D. Voloshko

V. Tszyu

K. Kim













































































































This document and its attachments, if any, contain confidential and proprietary information belonging or entrusted to UZBEKISTAN GTL LLC. The intended recipient(s) shall not divulge this information to any third party or sell, trade, publish, reproduce or reverse engineer any of the information contained herein, in any manner, without UZBEKISTAN GTL LLC’s prior written consent, and shall not put in use the information for any purpose unrelated to that for which it has been provided. Any disclosure and use of the contents hereof shall be further subject to any subsisting confidentiality undertakings between UZBEKISTAN GTL LLC and the intended recipient(s). The copyright in this document and its attachments, if any, is owned by UZBEKISTAN GTL LLC or its licensors, and any reproduction or adaptation thereof shall require UZBEKISTAN GTL LLC‘s express prior written approval.



Revision log


REV. NO.

REV. DATE

REVISED PARA.

REVISION DESCRIPTION















































































































































































































































































































































































































CONTENT

1.

PURPOSE

3

2.

SCOPE OF APPLICATION

3

3.

NORMATIVE REFERENCES

3

4.

SYMBOLS AND ABBREVIATIONS

4

5.

ОENERAL INSTRUCTIONS

5

6.

AREA OF LIABILITY

5

7.

COMPOSITION OF AS BUILT DOCUMENTATION

6











1. PURPOSE

The purpose of the development of this methodology is to define unified requirements for the procedure for filling out the forms of the executive documentation for the installation of reservoirs provided for by regulatory documents of the Republic of Uzbekistan, as well as the unified procedure for issuing and verifying executory documentation by all interested parties.

2. SCOPE OF APPLICATION

This methodology applies to the execution documentation for the installation of the reservoirs of the UzGTL-KNA project -VES-12-Xxx-O-xxx and establishes the requirements for the procedure for issuing the executive documentation for the installation of reservoirs during construction.

This method is the guiding document for the mandatory application by specialists of contractor and subcontractor organizations carrying out the construction of Unit 40,71,72,76,77,83,84,87, representatives of the technical supervision of the Owner, who supervises the construction and installation works, representative’s supervision, experts of other organizations acting on behalf of the Owner.

If the reference document is canceled (replaced by another one), then using the current instruction should be guided by the latest version of the new document. If the reference document is canceled without replacement, the provision referring to it is applied in a part that does not affect the construction legislation of the Republic of Uzbekistan.

3. NORMATIVE REFERENCES

This document uses references to the following regulatory documents:

  • ShNK 3.01.01-03 «Organization of construction production»;

  • КМК 3.05.05-98 «Technological equipment and process pipelines»;

  • VSN 478-86 «Production documentation for the installation of process equipment and process pipelines»;

  • Standard API 650 «Welded tanks for oil storage»;

  • SHNK 3.01.03-00 «Geodetic work in construction»;

  • КМК 3.03.01-98 «Supporting and protecting structures»;

  • КМК 3.03.02-98 «Metal structures. Rules for the production and acceptance of works»;

  • КМК 3.04.02-97 «Защита строительных конструкций и сооружений от коррозии»;

  • КМК 2.03.11-96 «Protection of building structures and structures against corrosion»;

  • UZGTL-KHB-VES-PC-00-0-0003 05-E Coloring Procedure;

  • PEE UZGTL-EEN-QAS-PC-00-0-0059 00-E- Plan for inspections and tests for tanks constructed in the field;

  • PEE UZGTL-EEN-QAS-PC-00-0-0071 00-E –

  • Plan of inspections and tests for insulation and application of protective coating;

  • UZGTL-KHB-VES-PC-00-0-0034 00-E General Welding Procedure;

  • UZGTL-KHB-VES-PC-00-0-0039 00-E Procedure for marking welded joints;

  • UZGTL-KHB-VES-PC-00-0-0025 00-E Welding materials control procedure;

  • UZGTL-ЕЕN- CIV-PC-00-0-0001 00-R Methodical instructions for the conduct of executive documentation (construction work);


NOTE - By using this normative document, it is advisable to check the effect of the reference normative documents in accordance with the "List of legislative acts and the main regulatory and administrative documents in force in the Republic of Uzbekistan.

If the reference document is canceled (replaced by another one), then using the current instruction should be guided by the latest version of the new document. If the reference document is canceled without replacement, the provision referring to it is applied in a part that does not affect the construction legislation of the Republic of Uzbekistan.

4. SYMBOLS AND ABBREVIATIONS

Further, in the text of this Methodology, the following definitions should be understood in the following transcription:

RUz


-

The Republic of Uzbekistan;

Owner

-

ООО «Uzbekistan GTL»;


Authorized representative

Of the Customer

-

a person (organization or subdivision) documental authorized by the Customer to perform the functions of construction control (technical supervision) at the Site;


Designer

-

the organization carrying out, according to the technical task of the Owner, the development of design documentation for construction and architectural supervision of construction;

Executor

of work

-

the enterprise or its separate structural unit performing welding-assembly and / or painting works on the Site;

Object

-


Tanks vertical cylindrical steel project "UZGTL", located at the stage of new construction;

Norms

-


approving provisions in the existing normative documents, applicable for the construction of the facility;

Service

quality control

-

service providing non-destructive testing of finished welded joints with the issuance of documentary control results. It can be either a structural unit of the Contractor of works or a separate independent enterprise;


As built documentation

-


forms of executive and technical documentation, of which is formed, including. acceptance documentation;

Permit

documentation

-

documentation confirming the Contractor's right to perform works on the Facility;

Acceptance documentation

-

documentation, subject to transfer to the Customer upon completion of the construction of the Facility;

Project documentation

-

Project documentation

non-destructive control

-

non-destructive control

visual and measuring control.

-

visual and measuring control.


act of survey of concealed works

-

act of survey of concealed works, drawn up in accordance with UZGTL-EEN-CIV-PC-00-0-0001-00-R.


act of intermediate acceptance of responsible structures

-

act of intermediate acceptance of responsible structures, drawn up in accordance with UZGTL-EEN-CIV-PC-00-0-0001-00-R.


CIW

-

Construction and installation work

Installation work

-

Works on the installation of vertical cylindrical steel tanks;

Contractor of installation works

-

The enterprise or its separate structural unit carrying out the Installation work at the facility;


5. GENERAL INSTRUCTIONS

The order and sequence of the design of the as built documentation should be in accordance with the technology of construction and installation works.

Forms of documents that are not included in this Methodology, but which require registration, must be coordinated with the specialists of the Project Directorate and the authorized representatives of the Customer in the area of ​​specialization (welding, mechanic and assembly works, НРК и т.п.).

If there is any disagreement on the correctness of filling out the as built documentation, it is necessary to apply for clarification to the Owner.

6. AREA OF LIABILITY

  1. The contractor is responsible for the timely and high-quality design of the as built documentation for the completed construction and installation work. The Contractor is responsible for the transfer to the Owner of a set of acceptance documents for the constructed facility.

  2. Author's supervision of the Designer verifies the correctness of entering information in the as built documentation for compliance with the current project documentation, including approvals issued in the course of production.

The authorized representative of the Owner checks the design of the as built documentation for:

  • correctness of the design and/or technical data;

  • availability of the necessary cover documentation attached to the as built documentation;

  • conformity of as built documentation forms to the requirements construction of standards, regulations and acts on the territory of Uzbekistan;

  • • the correspondence of information in English to the Russian version of the text.

6. COMPOSITION OF as built documentation

Acceptance and acceptance permits, executed by the Contractor of works, confirming the qualification of the personnel, quality of the applied

materials and conformity of measuring instruments



п/п

Type of work


Document to be provided

Submission

period

1

Confirmation of authorities of officials responsible for as built documentation.

Orders for authorized persons responsible for maintaining and signing as built documentation forms, with the application of certified samples signatures of the indicated persons.

Before starting welding work and then on again involving construction.

2

Confirmation of the powers of the officials in charge of the work.

Orders on the appointment of authorized representatives for the quality and safety of work.

Orders on the appointment of responsible persons for the operation and safe movement of lifting mechanisms.

Orders on the appointment of responsible persons for organizing the performance of welding operations and the implementation of industrial control over compliance with industrial safety requirements.

Orders on the appointment of responsible persons for the organization of loading and unloading operations.

The order on appointment of the responsible executor on conducting geodetic works.


3

Confirmation of the specifications of technological procedures for welding production.

Written procedures for welding technology and technological welding cards approved by the Customer. Written operational technological maps on anti-corrosion welded joints.

4

Confirmation of the qualification of welders.


Order on awarding stamps to staff welders. Protocol of the annual certification of welders. Act test control

samples of welders. Copies of qualification certificates.

Before the beginning of welding works and then on again involved construction.


5

Confirmation of compliance of a special tool, welding equipment.

Certified copies of certificates of verification of measuring instruments, welding equipment.

6

Confirmation of qualification of the welding procedure

Protocol for the qualification of the welding procedure specifications (PQR). Written Welding Procedure Specification (WPS), approved by the Owner


7

Confirmation of welders / welding operators qualification

Protocol for the qualification of the welding procedure specifications (PQR). Written Welding Procedure Specification (WPS), approved by the Owner.

8

Confirmation of powers of officials in charge of welding operations

Orders on the appointment of responsible for the quality and safety of welding operations.

9

Confirmation of powers of officials, guiding of anti-corrosion welded joints, building structures

Orders on the appointment of those responsible for the high-quality and safe performance of anticorrosion works.

10

Confirmation of conformity of welding equipment

Certified copies of certificates of verification of measuring equipment installed in welding equipment and in welding equipment.

11

Confirmation of conformity of consumable welding consumables

Quality certificates for the welding materials used (the composition of the welding materials must comply with WPS). Acts of incoming control.

Before the beginning of welding works and then on again involved construction

12

Confirmation of conformity of paint materials

Quality certificates for the applied painting systems (for each component). Acts of incoming control.

13

Confirmation of compliance of tank components

Acts of entrance control for the sheets of bottoms, walls, roofs, pits, rafters, compression rings, steel / constructions of ladders, attachments.

Acceptance documentation, executed by the Contractor of works,

confirming the volume and quality of the work performed:




Type of work

Document to be provided

Submission

period

14.

Welding and installation works on the construction site

Welding works log. Executive drawing. The act of geodetic control. The executive geodetic scheme.


On demand

in the course of work.

15.


Installation work

The log book of installation of construction structures. The act of geodetic control. Executive drawing. The executive geodetic scheme.


16.


Carry out anti-corrosion protection of welded joints.

The log book of the production of anticorrosive works (concealed work acceptance certificate). Acceptance of protective coatings. The act of survey of hidden works (journal production of anticorrosion)